Smartsheet Resource Management is a separate add-on, sold only to Smartsheet Business and Enterprise customers and priced per user through sales, with no public price list. It schedules named people across projects, shows allocation heatmaps and tracks time and fees. It does not rank proposals or decide what gets funded, so it fits a PMO whose problem is staffing approved work, not choosing it.
Most teams meet the add-on at the same moment: the Smartsheet portfolio is in place, someone asks who is free next quarter, and the answer lives in five spreadsheets. Before you ask sales for a quote, it helps to know what the product is, what the vendor itself lists as its limits, and whether your real gap is people scheduling or portfolio capacity. If you are still deciding how far to stretch Smartsheet at all, start with our guide to Smartsheet project portfolio management.
Key takeaways
- Resource Management by Smartsheet is the former 10,000ft product, bought by Smartsheet in 2019 and run as its own application with its own login.
- It is available on Business and Enterprise plans only, priced per user, and quoted by sales on top of your Smartsheet seats.
- Workload tracking (who has how many tasks) is already included in Business and Enterprise. Capacity planning, time tracking, skills matching and utilization reports need the add-on.
- The official limitations list names no Gantt or dependencies, fixed dashboards and project level permissions only. Placeholders, roles and scenario planning are positioned as Enterprise features.
How much does Smartsheet Resource Management cost?
Smartsheet does not publish a price for Resource Management. The product page says the cost depends on the number of users and sends buyers to sales. It is bought on top of a Business or Enterprise subscription, so your total is the Smartsheet seats plus the add-on seats.
Third party listings still quote old 10,000ft per user figures, and the most cited one on a large review site was last updated in 2021. Treat any printed number as a starting point for negotiation, not a budget line. What you can control is the structure of the quote, and that is where most of the money sits.
| Cost line | Published? | What drives it | What to ask sales |
|---|---|---|---|
| Smartsheet Business or Enterprise seats | Business yes, Enterprise quoted | Every member who edits sheets | Whether viewers and commenters stay free |
| Resource Management users | No, quoted per user | Every person who is scheduled, logs time or plans | Is a scheduled person who never logs in a paid user, and is there a price for time-only users |
| Enterprise features inside Resource Management | No | Placeholders, roles, disciplines and scenario planning | Which of these your tier includes, in writing |
| Professional services for onboarding | No | Number of projects, custom fields and integrations | A fixed price and a named deliverable list |
Swipe to see more →
The question in the second row decides the bill. A resource tool is only useful if everybody you schedule is in it, so a 120 person delivery organisation is a 120 person licence count, even if only six managers ever open the planning screen. For the base plan prices and how a Smartsheet stack compares with a full suite at 60 users, see our Planview vs Smartsheet pricing breakdown.
Does Smartsheet have resource management?
Yes, in two layers. Business and Enterprise plans include workload tracking, which counts assigned tasks per person across sheets. Real capacity planning, with availability, holidays, percentage allocations, time tracking and utilization reports, is the separate Resource Management by Smartsheet product. It runs as its own application and connects to Smartsheet projects.
What the add-on covers and what the vendor says it does not
Smartsheet is unusually candid about the product. Its help center publishes an overview and limitations page, and it is the best document to read before a demo. In short, the tool is strong on people and hours and deliberately thin on project structure.
| Area | What Resource Management does | What the official limitations list says |
|---|---|---|
| Scheduling people | Visual schedule matching people to projects, allocation in percent across several projects | No task level tracking, subtasks or dependencies |
| Capacity | Availability with PTO and holidays, over and under allocation, heatmaps | Scenario modeling listed as missing; product page now offers scenario planning on Enterprise |
| Matching | Assign by skill, location or qualification, find suitable unassigned people | None listed |
| Time and money | Timesheets, time and fee forecasts, budget by phase, expense reports | None listed |
| Reporting | Pre-built and custom reports by attribute, utilization report | Dashboards cannot be customized |
| Security | Smartsheet authentication or SSO | Project and account level permissions only, no column level or dynamic permissions |
Swipe to see more →
Two of these matter more for a portfolio office than for a delivery team. The first is the scenario question. The help center still lists scenario modeling as a limitation, while the product page now advertises what-if planning with placeholders, roles and disciplines on Enterprise. Ask for that exact screen in the demo, on your tier, before you count on it. The second is permissions: if finance rates or salaries must be hidden from project managers, project level permissions may not be fine-grained enough.
A worked capacity check by role
Here is a test to run before you buy any resource tool. Take one real quarter and one real delivery pool. In this example the pool has 12 developers, 4 data engineers and 3 business analysts, each with about 120 bookable hours a month after leave, meetings and support, so 360 hours a quarter per person.
| Role | Quarterly capacity | Demand from approved projects | Load | Plus proposal P5 |
|---|---|---|---|---|
| Developers (12) | 4,320 h | 4,100 h | 95% | 4,420 h, 102% |
| Data engineers (4) | 1,440 h | 1,520 h | 106% | 1,880 h, 131% |
| Business analysts (3) | 1,080 h | 760 h | 70% | 880 h, 81% |
Swipe to see more →
Resource Management is very good at the middle columns. Once named people are scheduled on approved projects, the heatmap shows two data engineers in red and the analysts with room, and a resource manager can move work between people in minutes. That is the staffing job, and the add-on does it well.
The portfolio question is the last column. Proposal P5 is not approved yet, it has no named people, and it needs 360 data engineer hours, which is a full person for the quarter in a role that is already at 106%. To see that before the steering group meets, you need the proposal in the plan as role demand rather than named assignments, and you need it next to the other proposals in priority order. In Resource Management that means tentative projects with placeholders, which the vendor positions as an Enterprise feature. On Business, P5 usually stays in a spreadsheet until it is approved, which is exactly when the conflict becomes expensive.
The decision the steering group actually needs is short: approve P5 and delay the lowest ranked data project, approve P5 and hire or contract one data engineer, or defer P5 a quarter. That is a portfolio decision made on role level numbers, and it is the gap our resource capacity planning tool is built for, with demand by role for twelve months set against the ranked list and the funding line. Our article on resource capacity planning for project portfolios walks through building that view from scratch.
Is Smartsheet Resource Management the same as 10,000ft?
Yes. Smartsheet acquired 10,000ft in 2019 and renamed it Resource Management by Smartsheet. It still runs as a separate application with its own sign-in and data model, connected to Smartsheet projects rather than built into the grid. Older guides and price listings that mention 10,000ft describe the same product, often with outdated prices.
Is Resource Management included in Smartsheet Business?
No. Business and Enterprise include workload tracking, which shows how many tasks each person holds. Resource Management, with capacity planning, time tracking, skills matching and utilization reports, is a separate paid product available to Business and Enterprise customers. Pro customers would have to move up to Business before they can buy it.
Where the add-on wins and where a different tool fits better
Being fair to it: for a services firm or an internal delivery team that already plans projects in Smartsheet, Resource Management is often the shortest path. The data stays in one vendor, time and fee forecasts work out of the box, and the heatmap is easy for managers to read. It wins most clearly when the main question is who works on what next week and how many billable hours the month will produce.
| Your main problem | Best fit | Why |
|---|---|---|
| Assigning named people to approved projects | Resource Management by Smartsheet | Heatmaps, percent allocations and skill matching across Smartsheet projects |
| Billable utilization and fee forecasts | Resource Management by Smartsheet | Time and fee forecasts and utilization reports are built in |
| Seeing overload in task assignments only | Workload tracking already in your plan | No add-on needed if task counts answer the question |
| Deciding which proposals fit the capacity you have | A role-based portfolio capacity tool | Proposals sit as role demand next to the ranked list before anyone is named |
| Capacity plus funding, gates and governance across business units | A PPM suite | Financials and governance at a scale Smartsheet does not target |
Swipe to see more →
If the third row describes you, read our comparison of workload management software first, because many teams buy a resource tool when a workload view would have been enough. If you are weighing the add-on against dedicated tools, our list of the best capacity planning software groups the options by the job they do.
Five questions to settle before you sign
- Who is a paid user? Get the rule for people who are scheduled but never log in, and for time-only users.
- Which tier unlocks placeholders and scenarios? If proposals must be planned before approval, this is the feature you are buying.
- How do projects get in? Ask how Control Center creates projects in Resource Management and which custom fields carry over.
- Who sees rates? With project and account level permissions only, check that bill rates and costs stay where they should.
- What does onboarding cost? Get a fixed price for setup, role lists and the first import, not a day rate.
Most PMOs write the business case for the add-on themselves, and many now draft it with an AI assistant and then edit it so it reads like the PMO lead wrote it, by hand or with a rewriting tool such as Undetected. Whatever the drafting route, put the role level table above in the document. A steering group approves a resource tool faster when it sees the conflict it will prevent, in hours, for a real quarter.
Who should buy it
Buy Resource Management if Smartsheet is your system of record for projects, the team you schedule is mostly the team in Smartsheet, and your daily problem is assigning people and forecasting hours. Look elsewhere, or add a decision layer, if the arguments in your portfolio meetings are about which proposals to start and whether the roles exist to deliver them. That second problem is solved on role level numbers before anyone is named, and it is cheaper to solve it there than to license every person in the delivery organisation to find out.